Paving List

Paving and resurfacing is done in coordination with the Georgia Department of Transportation's (GDOT) Local Maintenance Improvement Grant (LMIG).

The LMIG paving list for 2024 was approved Jan. 16, 2024.


See interactive Paving Map here

Image of Paving Map 5/22

2024 LMIG Project List

Road Name Beginning Ending Length (Miles) Description of Work District Status
Greenwich Dr. Barcelona Dr. Cul De Sac 0.26 Resurfacing 1 Planned
Granville Ln. Barcelona Dr Cul De Sac 0.07 Resurfacing 1 Planned
Cheyenne Dr. Rocky Plains Rd. Harvey Wood Dr. 0.53 Resurfacing 1 Planned
Harvey Wood Dr. Cul De Sac Cul De Sac 0.36 Resurfacing 1 Planned
Cranbrook Ct. Cheyenne Dr. Cul De Sac 0.15 Resurfacing 1 Planned
Cindal Ct. Cheyenne Dr. Cul De Sac 0.06 Resurfacing 1 Planned
Scouts Ridge Dr. Scout Rd. Cul De Sac 0.44 Resurfacing 1 Planned
Cub Ln. Scouts Ridge Dr. Cul De Sac 0.28 Resurfacing 1 Planned
Frankie Ln. Hwy 36 Cul De Sac 0.55 Resurfacing 1 Planned
Hugh Dr. Freeman Dr. Cul De Sac. 0.72 Resurfacing 2 Planned
Butler Bridge Rd. Freeman Dr. Cul De Sac 0.73 Resurfacing 2 Planned
Salem Branch Dr. Salem Branch Rd. Cul De Sac  0.18 Resurfacing 2 Planned
Salem Branch Ct. Salem Branch Rd. Cul De Sac 0.07 Resurfacing 2 Planned
Salem Branch Rd. Brown Bridge Rd. Cul De Sac 0.38 Resurfacing 2 Planned
Tara Way Oak Hill Rd. Cul De Sac 0.33 Resurfacing  2 Planned
Tara Ct. Tara Way Cul De Sac 0.09 Resurfacing 2 Planned
Saddlebrook Dr. Kirkland Rd. Valley Brook Dr. 0.43 Resurfacing 3 Planned
Oak Terrace Dr. Oak Manor 
Dr.
Hillside Oak Ln. 0.41 Resurfacing 3 Planned
Arbor Lake Dr. Oak Terrace Dr. Silver Willow Walk 0.11 Resurfacing 3 Planned
Silver Willow Walk Arbor Lake Dr. Oakwood Dr. 0.66 Resurfacing 3 Planned
Lakeview Trl. Gross lake Pkwy Lakeview Trl. 0.03 Resurfacing 3 Planned
Lakeview Trl. Cul De Sac Cul De Sac 0.32 Resurfacing 3 Planned
Towers Rd. Dial Mill Rd. Cul De Sac 0.27 Resurfacing 3 Planned
Stonecreek Pkwy Fieldstone Ln. Cul De Sac 0.31 Resurfacing 4 Planned
Stonecreek Ln. Stonecreek Pkwy Cul De Sac .06 Resurfacing 4 Planned
Pond View Ct. Stonecreek Pkwy Cul De Sac 0.04 Resurfacing 4 Planned
Fieldstone Ln. Brown Bridge Rd. Trelawney Subdivision Entrance 0.37 Resurfacing 4 Planned
Knights Cir. Salem Rd. End 0.36 Resurfacing 4 Planned
Knights Dr. Knights Cir. End 0.11 Resurfacing 4 Planned
River North Ct. Upper River Rd. Cul De Sac 0.26 Resurfacing 4 Planned
Hillcrest Rd. SR 81 S. Lovers Lane Rd. 0.20 Resurfacing 4 Planned
Briarpatch Dr. Alcovy Rd. Cul De Sac 0.69 Resurfacing 5 Planned
Piper Rd. East End Rd. Craines View 0.57 Resurfacing 5 Planned
Dixie Ln. Dixie Rd. Circle Loop 0.57 Resurfacing 5 Planned
Bachelor Rd. Hwy 36 Cul De Sac 0.24 Resurfacing 5 Planned

2023 LMIG Project List

Road Name Beginning Ending Length (Miles) Description of Work District Status
Brittney Lane Rocky Plains Rd Cul De Sac .32 Patch and Resurface 1 COMPLETED
June 23
Brookhollow Way Loyd Rd Cul De Sac .53 Patch and Resurface 1 COMPLETED April 23
Spring Ct Brookhollow Way Cul De Sac .17 Patch and Resurface 1 COMPLETED April 23
Willow Dr. Willow Wood Rd Adams Circle .21 Patch and Resurface 1 COMPLETED April 23
Dukes Rd. Gaithers Rd.  S.R. 11 1.30 Patch and Resurface 1 COMPLETED March 23
West Forest Dr. Oaks Hill West Cul De Sac .35 Patch and Resurface 2 COMPLETED Feb. 23
Oak Hill West S.R. 20 S.R. 212 .37 Patch and Resurface 2 COMPLETED Feb. 23
Stone Creek Dr. S.R. 20 Cul De Sac .19 Patch and Resurface 2 COMPLETED March 23
Pebble Blvd. No. 485 No. 795/760 .48 Patch and Resurface 2 COMPLETED
Aug. 23
Pebble Brooke Pass No. 195 Pebble Blvd. .29 Patch and Resurface 2 COMPLETED
Aug. 23
Woodland Rd. Brown Bridge Rd. Forest Rd. .22 Patch and Resurface 2 COMPLETED
Aug. 23
Coldwater Dr. Hwy. 212 Cul De Sac .5 Patch and Resurface 2 COMPLETED
Carmel Dr. Coldwater Dr. Cul De Sac .11 Patch and Resurface 2 COMPLETED
Coldwater Way Coldwater Dr. Cul De Sac .16 Patch and Resurface 2 COMPLETED 
Valley View Rd. Bailey Creek Rd.  Rockdale County Line .12 Patch and Resurface 2 COMPLETED Feb. 23
Kent Rock Rd. S..R. 138 Walton County Line .79 Patch and Resurface 3 COMPLETED April 23
Natalie Ct. Jack Neely Rd. Sammy Ct. .18 Patch and Resurface 3 COMPLETED
July 23
Bowen Way Natalie Ct. Cul De Sac .34 Patch and Resurface 3 COMPLETED 
July 23
Cherohala Ct. Bowen Way Cul De Sac .21 Patch and Resurface 3 COMPLETED
July 23
Suzy Ct. Bowen Way Cul De Sac .05 Patch and Resurface 3 COMPLETED 
July 23
Carriage Park Ct. Bald Rock Rd. Cul De Sac .28 Patch and Resurface 3 COMPLETED May 23
Doubles Dr. Brown Bridge Rd. Cul De Sac .45 Patch and Resurface 3 COMPLETED
Aug. 23
Rodney Way Doubles Dr. Cul De Sac .23 Patch and Resurface 3 COMPLETED
Aug. 23
Roseberry Ct. Old Atlanta Hwy. Cul De Sac .05 Patch and Resurface 4 COMPLETED
Aug. 23
East Dollar Cir. 1-20 Access Rd. End .47 Patch and Resurface 4 COMPLETED 
May 23
Hegwood Dr. S.R. 81 S End .13 Patch and Resurface 4 COMPLETED
June 23
Whitehead Dr. Mote Rd. Cul De Sac .42 Patch and Resurface 4 COMPLETED
June 23
Whitehead Ct. Whitehead Dr. Cul De Sac .10 Patch and Resurface 4 COMPLETED
June 23
Highwood Dr. Fire Tower Rd.  Cul De Sac .38 Patch and Resurface 4 COMPLETED June 23
Fernwood Ct. Highwood Dr. Cul De Sac .04 Patch and Resurface 4 COMPLETED June 23
Wayland Ct. Highwood Dr. Cul De Sac .03 Patch and Resurface 4 COMPLETED June 23
Beachwood Ct. Highwood Dr. Cul De Sac .04 Patch and Resurface 4 COMPLETED June 23
Auburn Ct. Highwood Dr. Cul De Sac .09 Patch and Resurface 4 COMPLETED June 23
Byrd Rd. W. Macedonia Church Rd. Gum Creek Rd. 1.24 Patch and Resurface 5,3 COMPLETED May 23
Mount Tabor Rd. Sockwell Dirt .98 Patch and Resurface 5 COMPLETED
May 23
Geoffrey Ln. Ellington Rd. Walton County Line .48 Patch and Resurface 5 COMPLETED May 23